E.5 Production process & QC hold points per project

Each project has its own process according to its technical requirements (e.g. Tack-up for built-up girders, a QC hold point before welding). A HOLD point prevents later stages from exceeding the quantity accepted by QC.

What it does

  • Reorder, enable / disable, rename (VI / EN), colour and inspection criteria per stage; apply by component type, mark or profile.
  • Insert QC steps from the library (incoming material, fit-up, VT, UT / MT, Sa 2½ blasting, DFT, release for shipment…).
  • Copy the process from another project; disabling a stage does not delete data already ticked.