Compare 2–20 projects against a baseline project to see differences in weld density, deposited metal and consumables per tonne. Forecast consumables for a new project as a range (e.g. 4,400 – 4,950 kg) from similar projects – supporting fast quotations.

What it does

  • Warnings when comparing data of a different nature (not approved, estimate only, different method / scope / currency); system conclusions never infer cost from density.
  • 10 filterable analytics charts; historical data for projects not held in the system.
  • Forecasts carry a qualitative confidence level, adjustments with reasons and approval.