A
- Anchor bolt
- Bolt cast into the foundation that holds a column base plate. Its position, level and projection are surveyed before erection. Lihat juga: Steel erection: sequence, stability and site checks
- Assembly
- A fabricated piece made of a main part and the secondary parts welded or bolted to it in the shop, e.g. a column with its base plate and cleats. Lihat juga: B.4 Assembly, Part, Material take-off and Bolt lists
- Assembly mark
- The identifier given by Tekla numbering to identical assemblies (e.g. RF-1). It describes a type of piece; each physical piece also gets a serial. Lihat juga: Component identity: mark, serial, PCID and QR
- Awaiting QC
- Status of a production stage that the team has confirmed as completed but that still needs a QC inspection before the next stage can start. Lihat juga: Production statuses, hold points and NCR flow
B
- B/L (bill of lading)
- Transport document issued by the carrier for sea freight: receipt for the goods, evidence of the contract of carriage and document of title.
- BOM (bill of materials)
- The complete list of assemblies, parts, materials and bolts of a project with quantities, dimensions and weights, generated in PEB Studio from the IFC. Lihat juga: B.4 Assembly, Part, Material take-off and Bolt lists · B.9 Excel BOM & CSV export
- Built-up section
- An I-section welded from three plates (two flanges and a web) instead of being rolled. Typical for PEB frames, often tapered. Lihat juga: What is a pre-engineered building (PEB)?
C
- CC1–CC4 (construction category)
- Classes of AS/NZS 5131 that scale fabrication and erection requirements, similar to execution classes in EN 1090-2. Lihat juga: AS/NZS 5131 Structural steelwork – Fabrication and erection
- CHS / RHS / SHS
- Circular, rectangular and square hollow sections, written as Ø×t (CHS) or H×B×t (RHS / SHS). Lihat juga: Structural steel sections and how they are written
- CJP / PJP
- Complete and partial joint penetration butt welds. A CJP weld fuses the full thickness of the joint; a PJP weld only part of it. Lihat juga: Welding basics for steel fabricators
- Component Digital Passport
- The page opened by scanning a component on site: engineering, fabrication, QC, logistics, position, inspections, NCRs and photos of that piece. Lihat juga: I.2 Component Register, QR Scanner & Component Digital Passport
- CSC plate
- Safety approval plate on every container under the International Convention for Safe Containers, showing among others the maximum gross mass and tare. Lihat juga: Shipping structural steel in containers
- CTU Code
- IMO/ILO/UNECE code of practice for packing and securing cargo in containers and other cargo transport units. Lihat juga: CTU Code IMO/ILO/UNECE Code of Practice for Packing of Cargo Transport Units
- Cutting plan
- Layout of parts on stock sheets or bars that tells the cutting shop what to cut from which material, and purchasing how much to buy. Lihat juga: C.2 Plate and section cutting plan results · Cutting optimisation and how to keep scrap below 3 %
D
- DFT (dry film thickness)
- Thickness of a cured paint coat or system, measured in µm with a gauge – a standard QC record before release. Lihat juga: ISO 12944 Paints and varnishes – Corrosion protection of steel structures by protective paint systems
- Digital project dossier
- Online collection of released packing lists, shipping marks, reports, photos and certificates that the client opens from the QR code on a package. Lihat juga: H.10 International-standard shipping marks & digital project dossier
- DSTV / NC file
- Text file format for CNC drilling, sawing and cutting machines; its header contains the piece mark, which PEB Studio uses to link the file. Lihat juga: B.8 Drawings and fabrication files (PDF, DXF, NC/DSTV) · Supported file formats
- Dunnage
- Timber or other material used to support, separate and protect cargo in a container; wooden dunnage must comply with ISPM 15. Lihat juga: ISPM 15 Regulation of wood packaging material in international trade
E
- EXC1–EXC4 (execution class)
- Classes of EN 1090-2 that set the level of requirements for fabricating and erecting a steel structure; most buildings are EXC2. Lihat juga: EN 1090-2 Execution of steel structures – Technical requirements · Execution classes, ITPs and hold points
F
- Fillet weld
- Weld of roughly triangular cross-section joining two surfaces at an angle, as in a T-joint or lap joint. Sized by throat a or leg z (a ≈ 0.7 z). Lihat juga: Welding basics for steel fabricators
- Fit-up
- Positioning secondary parts on the main part and tack-welding them before full welding; usually followed by a dimensional check. Lihat juga: The steel fabrication process, step by step
G
- Girt
- Horizontal secondary member on a wall that carries the wall cladding to the columns, usually a cold-formed C or Z section.
- GUID
- Globally unique identifier of an object instance in the IFC model; PEB Studio shows it on the part and assembly pages. Lihat juga: Component identity: mark, serial, PCID and QR
H
- HDG (hot-dip galvanising)
- Corrosion protection by dipping fabricated steel in molten zinc, to ISO 1461. Lihat juga: ISO 1461 Hot dip galvanized coatings on fabricated iron and steel articles
- Heat number
- Number of the steel cast from which a product was made; it links a plate or section to its mill certificate. Lihat juga: Steel grades and mill certificates (EN 10204 3.1)
- Hold point
- Point in a process where work must stop until a defined inspection has been done and released. In PEB Studio, later stages cannot exceed the quantity accepted by QC. Lihat juga: E.5 Production process & QC hold points per project · Execution classes, ITPs and hold points
I
- IFC
- Industry Foundation Classes (ISO 16739), the open BIM exchange format. PEB Studio builds its BOM, 3D and identities from the IFC exported by Tekla Structures. Lihat juga: ISO 16739 (IFC) Industry Foundation Classes for data sharing in construction · B.1 Upload a Tekla project folder
- Incoterms
- ICC rules (e.g. FOB, CIF, DAP) that define which party pays for and bears the risk of each part of the transport. Never translated on documents.
- ITP (inspection and test plan)
- Document listing every inspection from incoming material to dispatch, with criteria, frequency, responsible party and hold / witness / review points. Lihat juga: Execution classes, ITPs and hold points
K
- Kerf
- Width of material removed by the cut (laser, plasma, saw). It is allowed for in nesting and cutting plans. Lihat juga: C.1 Settings & scrap-reduction levers
M
- Master PKL
- Packing list of a whole container, made of packages (Sub-PKL) and directly packed components. Lihat juga: Packing hierarchy: shipment, container, package
- MDR (manufacturer's data record)
- Quality dossier delivered to the client: certificates, WPS, welder qualifications, inspection and NDT reports, NCRs and coating records. Lihat juga: F.12 Traceability & audit log
- Method statement
- Document prepared by a competent person describing how a task – e.g. erection – will be done safely: equipment, sequence, temporary works and controls. Lihat juga: Steel erection: sequence, stability and site checks
- MR (material requisition)
- Internal request to purchase or issue material, generated in PEB Studio from the cutting plans with a 3-level signature block. Lihat juga: C.4 Material requisition (MR)
- MTC (mill test certificate)
- Inspection document from the steel mill, usually type 3.1 to EN 10204, with chemistry and mechanical test results of the delivered product. Lihat juga: EN 10204 Metallic products – Types of inspection documents
N
- NCR (non-conformance report)
- Record of a result outside the acceptance criteria, with disposition and corrective action. Flow: OPEN → CORRECTIVE ACTION → RE-INSPECTION → CLOSED. Lihat juga: F.8 QA/QC workflow, inspection queue & workshop NCR · Production statuses, hold points and NCR flow
- NDT (non-destructive testing)
- Inspection methods that do not damage the part: visual (VT), magnetic particle (MT), penetrant (PT), ultrasonic (UT) and radiographic (RT) testing. Lihat juga: Welding basics for steel fabricators
- Nesting
- Arranging part outlines on a sheet to minimise waste before cutting. Lihat juga: Cutting optimisation and how to keep scrap below 3 %
- Numbering (Tekla)
- Tekla Structures function that gives identical parts and assemblies the same mark. Must be run before exporting the IFC. Lihat juga: Exporting a clean IFC from Tekla Structures: checklist
P
- Part mark
- Identifier of identical single parts (plates, profiles) in the model; shown in the Parts list, on cutting plans and in NC files. Lihat juga: Component identity: mark, serial, PCID and QR
- PCID (Physical Component ID)
- Identifier of one physical component in Smart Erection (PC00001…), stable across model revisions and linked to its QR ID. Lihat juga: Component identity: mark, serial, PCID and QR · I.1 Erection dashboard
- PEB (pre-engineered building)
- Steel building whose frames, secondary members and cladding are designed as a system and fabricated for one project. Lihat juga: What is a pre-engineered building (PEB)?
- PKL (packing list)
- List of the contents of a package or container with weights and dimensions. Client copies are produced only from the released version. Lihat juga: H.2 PKL editor & eligible component selection · H.8 Client packing list
- Preloaded bolt
- High-strength bolt tightened to a specified tension so the joint resists slip by friction, supplied as a matched set (e.g. EN 14399). Lihat juga: Structural bolts: grades, sets and tightening
- Primary frame
- Columns and rafters of a PEB forming portal frames, usually built-up tapered sections. Lihat juga: What is a pre-engineered building (PEB)?
- Property class (bolts)
- Strength marking of metric bolts such as 8.8 or 10.9: first number × 100 = tensile strength in MPa. Lihat juga: Structural bolts: grades, sets and tightening
- Purlin
- Secondary roof member spanning between rafters that carries the roof sheeting, usually a cold-formed C or Z section. Lihat juga: B.3 Component groups
Q
- QR ID
- Code printed on a component label. It contains only the project, type, reference and an HMAC signature – no data or rights. Lihat juga: Component identity: mark, serial, PCID and QR · J.1 Server-side permissions & QR codes without rights
R
- Remnant
- Usable leftover of a sheet or bar above a minimum size (e.g. 300 × 300 mm plate, 1 m bar), returned to stock and not counted as scrap. Lihat juga: C.1 Settings & scrap-reduction levers
- Revision (R1, R2…)
- Numbered version of a weld register, handover dossier or document. Approved revisions are locked; changes create a new revision. Lihat juga: G.2 Recalculation from IFC, revisions, verification & approval · I.10 Digital Installation Handover & Reports
S
- Sa 2½
- Very thorough blast-cleaning grade of ISO 8501-1, the usual surface preparation for structural paint systems. Lihat juga: ISO 8501-1 Preparation of steel substrates before application of paints – Visual assessment of surface cleanliness
- Scrap rate
- Share of purchased material that becomes waste: 1 − net part weight ÷ gross material issued. PEB Studio targets 3 %. Lihat juga: Cutting optimisation and how to keep scrap below 3 %
- Serial (Item n / N)
- Number that identifies one physical piece among identical pieces of the same mark, printed on its label. Lihat juga: Component identity: mark, serial, PCID and QR
- SHA-256
- Cryptographic fingerprint stored with released documents and dossiers; any change to the file changes the hash, proving the document is the approved version. Lihat juga: Security and data principles
- Shipping mark
- Marking on a package (consignee, reference, destination, package n / N, handling symbols) per UN/ECE Rec. 15 and ISO 780. Lihat juga: UN/ECE Rec. 15 · ISO 780 Simpler shipping marks · Pictorial marking for handling of goods · H.10 International-standard shipping marks & digital project dossier
- Smart Erection
- PEB Studio module for site: receiving, storage, erection sequence, installation progress, inspections and the digital handover. Lihat juga: I.1 Erection dashboard
- Splice
- Joint made in a member that is longer than the available stock; at most one per part, with the position approved by the designer. Lihat juga: C.2 Plate and section cutting plan results
- Sub-PKL
- Packing list of one package inside a container, with its own number and QR label (e.g. PKG-0726-0001). Lihat juga: Packing hierarchy: shipment, container, package · H.3 Packages (Sub-PKL) & QR scan-to-pack
T
- Tack weld
- Short weld that holds parts in position during fit-up before the final welding.
- Throat thickness (a)
- Height of the largest triangle inscribed in a fillet weld; the size used in European practice (a ≈ 0.7 × leg). Lihat juga: Welding basics for steel fabricators
V
- VGM (verified gross mass)
- Total weight of a packed container that the shipper must declare before loading on a ship, under SOLAS chapter VI. Lihat juga: SOLAS VI/2 (VGM) Verified gross mass of packed containers
W
- Weld density
- Metres of weld per tonne of steel (m/t), used to compare projects and forecast consumables. Lihat juga: G.5 Project comparison, analytics & material forecast · Estimating deposited metal and welding consumables
- Welder qualification
- Certificate showing a welder passed a test for a process, position and range (e.g. ISO 9606-1); kept valid by 6-monthly confirmation. Lihat juga: ISO 9606-1 Qualification testing of welders – Fusion welding – Part 1: Steels
- Witness point
- Inspection point the client is notified of and may attend; work may continue if they do not. Lihat juga: Execution classes, ITPs and hold points
- WPQR / PQR
- Welding procedure qualification record: the test result that qualifies a welding procedure and supports one or more WPS. Lihat juga: ISO 15614-1 Specification and qualification of welding procedures – Welding procedure test – Part 1: Arc and gas welding of steels
- WPS (welding procedure specification)
- Document that tells the welder how to make a weld: process, consumables, position, thickness range, preheat and parameters. Lihat juga: F.11 WPS, PQR, welder qualifications & WPS authorisation · Welding basics for steel fabricators